Project: Rooftop Solar Power Plant of 10MW,
Industry: Electricity/ Energy
Type: Solar power generation
Estimated total investment: 13 million USD
Investment nature: Non governmental
Financial situation: not in place yet
Construction level: Industry medium standard
Scheduled construction date: June 2017
Estimated deadline: June 2019
Equipment source: Domestic procurement
Progress:Preparation for construction
Project Nature: New
Location:
Main equipments: PV batteries, PV components, DC distribution box, DC cables, inverters, low voltage distribution system, basic frame, power distribution cabinet etc.
Project information: Total installed capacity 20MW. Total investment: 13 million yuan.